UPDATED on August 5th

Wednesday, July 29th at the Wilmington Urban Area Metropolitan Planning Organization

 

RE: Cape Fear Memorial Bridge Public Meeting

A recent local news report (on WECT 6*) stated that the WMPO Board will be meeting on Wednesday at 3 pm, at which time a reported “$1 billion” bridge proposal will be considered.

 

Per the WECT 6 report, the proposal of the “private company” would be tall enough to permit the passage of “cargo ships” and be “financed by a toll.”

 

1.  There is no need for “cargo ships” to be able to pass further upstream than the current Wilmington port, which is below (south of) the current Memorial Bridge, nor would it be desirable for wakes caused by large cargo ships to damage or wash over Wilmington’s signature “Riverwalk,” should a future mega-bridge allow large or heavily laden ships to pass by Wilmington city;

&

2.  Citizens on both sides of the river oppose the very idea of a toll, not least if - as reliably reported - tolls would be collected by the “private company” long after the costs of bridge-building are recouped.

 

Results of this meeting?

a) The unsolicited bid will not go forward.

b)  Nobody spoke in favor of the 135-ft high bridge option; several people denounced it directly or asked for consideration of "other options".

c)  Most of the 14 speakers denounced the paying of tolls --- saying, e.g., that downtown businesses would suffer, and/or that it was an "unfair tax" on people who have to commute to work (& words to that effect).

d) Similarly, many speakers called on officials to find other ways of funding a new bridge.

e) Several speakers addressed problems with the scope of the area subject to, and/or criteria that seem lie behind, the "determination" that a 135-ft. high bridge should (probably) be built;  these problems did or could include: insufficient environmental impact studies; the definition / revision of "channel" or "harbor" area [linked, in turn, to:  Section 14 of the Rivers and Harbors Act of 1899 (33 U.S.C. §408), perhaps]; the economics / funding of the mega-bridge project [in terms of winners, losers, conflicts of interest, etc..]  

Funding & Tolling

  • WMPO must vote by February 2027 to approve tolling or withdraw the project, which would eliminate state funding and cancel the federal grant.

  • Without tolling, no alternative funding source currently exists.

  • Tolling options under discussion include:

    • State‑managed toll (NC Turnpike Authority)

    • Private‑public partnership (Delivering Bridges LLC proposed ~$2.75 per trip)

Environmental Review & Timeline

  • Environmental Assessment (EA) expected late spring–summer 2026, followed by a public hearing.

  • Federal permitting continues through March 2029 (permitting dashboard).

  • Key milestones:

    • EA release — Spring/Summer 2026

    • Public hearing — Summer 2026

    • Preferred alternative — Fall 2026

    • FONSI — Winter 2027

    • “Shovel‑ready” deadline — September 2027 (required to keep federal grant)

Community Positions

Wilmington Chamber of Commerce

  • Supports the 135‑ft fixed bridge.

  • Argues it is the best long‑term investment, accommodates future growth, and avoids costly maintenance associated with movable spans.

  • Frames the project as essential for Wilmington’s competitiveness with cities like Charleston and Savannah.

  • Chamber stance summary:

    • Pro fixed bridge

    • Pro long‑term capacity

    • Pro modern infrastructure investment

Residents of Old Wilmington (ROW)

  • ROW members submitted a public letter expressing strong concerns about the current plans.

  • Their position emphasizes “Do no harm” and argues the proposed designs will:

    • Harm local economy and traffic flow

    • Damage historic neighborhoods

    • Affect evacuation routes

    • Impose significant toll burdens on residents (~$1,500/year for commuters)

  • ROW supports the 65–135 ft lift bridge, which maintains the existing footprint and avoids shifting entry/exit points into historic areas.

  • ROW stance summary:

    • Pro lift bridge

    • Anti fixed bridge footprint expansion

    • Anti tolling burden on residents

ARTICLES

Coastal Review - July 24, 2026

Few public projects have generated as much discussion in southeastern North Carolina as the proposed replacement of the Cape Fear Memorial Bridge. Citizens have raised thoughtful questions about the bridge’s cost, the possibility of tolls, impacts on surrounding neighborhoods, and perhaps most notably, one simple question: Why does the replacement bridge need to be 135 feet high?...

Read more at Coastal Review, coastalreview.org.

WHQR - June 30, 2026

“Do no harm” is a phrase commonly associated with the medical profession’s oath, but it is increasingly applied to corporations, government organizations, and their regulators. Do no harm should guide NCDOT and the Wilmington Metropolitan Planning Organization with the plans to replace the Cape Fear Memorial Bridge. Unfortunately, the current plans fall short of this goal and will harm the local economy, traffic flow, the environment, and evacuation routes...."

Read more at WHQR, https://www.whqr.org/local/2026-06-30/letter-to-the-editor-residents-weigh-in-on-replacing-the-cape-fear-memorial-bridge

TIMETABLE

Bridge Project Timeilne-July 27 2026.png